I’ve seen many attempts to answer these questions in a few sentences, and all such attempts always lead to more confusion than clarification. Downloadzpdf tells you the truth about passing the exam: The latest version of the CompTIA Project+ exam PK0-004 dumps update https://www.pass4itsure.com/pk0-004.html, the real CompTIA Project+ exam material, to help you easily pass the exam and get advanced certification (CompTIA Project+).

CompTIA Project + Exam PK0-004 Dumps New

If you would like to learn more about the CompTIA Project+, please go to the official website. Also, you may want to learn about the PK0-004 exam practice questions for more help. Downloadzpdf will help you, you can take the free practice test below, free questions provided by the latest version of the CompTIA Project + dumps, feel free to use.

CompTIA Project + exam test PK0-004 Q&As

# QUESTION 1

During the execution phase, the project manager discovered that the testing phase is dependent on completion of the vendor\\’s tasks. The project team has just informed the project manager their activities are almost complete, and they would like permission to begin testing. The vendor is not scheduled to deliver the products for two months.

Which of the following should have occurred to prevent this issue?

A. During the planning phase, the project manager should have recognized the relationship between the vendor\\’s and project team\\’s tasks and adjusted the schedule for the project team to begin activities two months later.

B. The project manager should have crashed the schedule for the vendor to keep it at the same work pace as the rest of the project team.

C. During the project team\\’s regular status meeting with the vendor, the project team should have informed the vendor that the team was ahead of schedule and to speed up their work.

D. During the project team\\’s regular status meeting with the vendor, the vendor should have informed the project team that it required another two months, and to slow down.

Correct Answer: B

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 170

# QUESTION 2

The project sponsor has cut the resources required for project completion. The project manager cannot complete the project without additional resources.

Which of the following should the project manager do to obtain the resources?

A. The project manager should identify and document the reasons for the additional resources in a change request.
B. The project manager should hire additional resources temporarily to complete the project.
C. The project manager should terminate the project until additional resources are added to the project.
D. The project manager should ask the project team members to take on more tasks to complete the project on time.

Correct Answer: A

# QUESTION 3

Which of the following activities are associated with the closing phase of a project? (Choose two.)

A. Risk mitigation
B. Archiving of project documents
C. Tracking of expenditures
D. Lessons learned
E. Quality assurance

Correct Answer: BD

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 338,

# QUESTION 4

A project manager needs to identify the resources assigned to a particular task. In which of the following documents can this information be found?

A. Project schedule
B. Cost plan
C. Scope statement
D. Impact assessment

Correct Answer: A

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 156

# QUESTION 5

A stakeholder with whom the project manager has worked on numerous occasions drops by and requests that the project management add two small items to the application under development.

The stakeholder has seen the value of these changes in other applications and assures the project manager they are easy, quick changes. Which of the following BEST describes how the project manager should respond?

A. Take the request to the CCB
B. Quickly make the changes
C. Ask a project team member to make the changes
D. Inform the sponsor of the stakeholder\\’s request

Correct Answer: C

# QUESTION 6

Which of the following should be used to identify where slack is occurring in the project schedule and determine the critical path? (Choose two.)

A. PERT chart
B. Risk register
C. Arrow diagram method
D. RACI matrix
E. Project charter
F. Fishbone diagram

Correct Answer: AF

# QUESTION 7

The design activity of a project has the following cost attributes:
PV = 100,000 EV = 20,000 AC = 90,000
Based on this scenario, calculate the schedule variance.
A. -80,000
B. -70,000
C. 10,000
D. 120,000

Correct Answer: A

# QUESTION 8

A vendor advises the project manager that a key component of the project is no longer available and recommends a higher-cost replacement. To have this change approved, the project manager submits a change request that contains which of the following?

A. Description, cost difference of the replacement, and WBS
B. Description, justification, and cost
C. Cost difference of the replacement, justification, and communications plan
D. Description, quality impact, and cost

Correct Answer: B

# QUESTION 9

According to the communication management plan, the project scheduler is required to post weekly status reports on the project\\’s intranet site. From the stakeholders’ point of view, accessing the weekly report is an example of:

A. interorganizational preferences
B. personal preferences
C. the interactive method
D. the pull method

Correct Answer: D

# QUESTION 10

A project sponsor promises the Chief Executive Officer (CEO) that a project will be completed before the next quarterly meeting. The project manager needs to take the following elements into account:
Delivery Vacation Cost of overtime Work effort

Which of the following documents should the project manager use to guarantee the project\\’s success?

A. RACI
B. Schedule
C. Project charter
D. SWOT
E. Burn chart

Correct Answer: E

# QUESTION 11

A company is hired to perform some of another organization\’s work. Which of the following types of organizational change is described?

A. Outsourcing
B. Business process change
C. Shared resources
D. Split

Correct Answer: A

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 297

# QUESTION 12

An organization is divided into three separate entities based on geographical region. Which of the following types of organizational change is this?

A. Relocation
B. Outsourcing
C. Demerger
D. Split

Correct Answer: D

……

CompTIA PK0-004 free dumps pdf online download:

[from google drive] https://drive.google.com/file/d/1NaN6_aSh1eypQsgl6d3gxWeGjolnazbv/view?usp=sharing

There are a number of requirements that must be met to pass the CompTIA Project+ exam: first, you need to have the latest PK0-004 dumps of real CompTIA Project+ exam materials, and secondly, you need to work hard to practice the PK0-004 exam questions.

Of course you can take the free practice test (some questions) provided above first, and then get the full CompTIA PK0-004 dumps https://www.pass4itsure.com/pk0-004.html (unique questions 727+ ).

If you want to know more about CompTIA, please click to view https://www.downloadzpdf.com/category/comptia-exam-practice-questions/